    77== Steps & Dates == 
    88 
    9 1. Cleaning out space 
    10  a. Clear logs 
    11  a. Remove existing testing.engagemedia.org files 
    12  a. Setup videos.testing.engagemedia.org under /var/www to store freshly transcoded videos 
    13 1. Setup new clean Plumi 0.2.x installation 
    14  a. Create /opt/backup/plumi2 
    15  a. Copy over production Data.fs & var/files  
    16  a. Test & verify copied data is working correctly 
    17 1. Install a new Plumi 3 site under testing.engagemedia.org 
    18 1. Migrate data from Plumi 0.2.x installation to testing.engagemedia.org  
    19 1. Migrate the engagemedia.org theme from Plone 2.5 to Plone 3 so it will work with Plumi 3  
    20 1. Apply new theme to testing.engagemedia.org'''(complete by 2010-04-09 12:00 GMT)''' 
    21 1. Thorough testing of testing.engagemedia.org by EM staff '''(complete by 2010-04-14 08:00 GMT)''' 
     9 1. Cleaning out space 
     10  a. Clear logs 
     11  a. Remove existing testing.engagemedia.org files 
     12  a. Setup videos.testing.engagemedia.org under /var/www to store freshly transcoded videos 
     13 1. Setup new clean Plumi 0.2.x installation 
     14  a. Create /opt/backup/plumi2 
     15  a. Copy over production Data.fs & var/files  
     16  a. Test & verify copied data is working correctly 
     17 1. Install a new Plumi 3 site under testing.engagemedia.org 
     18 1. Migrate data from Plumi 0.2.x installation to testing.engagemedia.org  
     19 1. Migrate the engagemedia.org theme from Plone 2.5 to Plone 3 so it will work with Plumi 3  
     20 1. Apply new theme to testing.engagemedia.org'''(complete by 2010-04-09 12:00 GMT)''' 
     21 1. Thorough testing of testing.engagemedia.org by EM staff '''(complete by 2010-04-14 08:00 GMT)''' 
    2222 
    2323Once we have completed testing and are ready to go live into production we will: 
    2424 
    25 1. Prepare for production migration 
    26  a. Clear out /opt/backup/plumi2 and reinstall a fresh Plumi 0.2.x system 
    27  a. Copy over production Data.fs & var/files 
    28  a. Test & verify copied data is working correctly 
    29 1. Take engagemedia.org offline 
    30 1. Backup entire /opt/colli-instances/www.engagemedia.org  
    31 1. Erase /opt/colli-instances/www.engagemedia.org files 
    32 1. Install new Plumi 3 site under /opt/colli-instances/www.engagemedia.org 
    33 1. Migrate data from Plumi 0.2.x installation to www.engagemedia.org '''(complete by 2010-04-15 12:00 GMT)''' 
    34 1. Apply new engagemedia.org theme from testing.engagemedia.org into www.engagemedia.org 
    35 1. Test to verify new www.engagemedia.org is operational '''(complete by 2010-04-15 14:00 GMT)''' 
    36 1. Open engagemedia.org to the public '''(complete by 2010-04-15 16:00 GMT)''' 
     25 1. Prepare for production migration 
     26  a. Clear out /opt/backup/plumi2 and reinstall a fresh Plumi 0.2.x system 
     27  a. Copy over production Data.fs & var/files 
     28  a. Test & verify copied data is working correctly 
     29 1. Take engagemedia.org offline 
     30 1. Backup entire /opt/colli-instances/www.engagemedia.org  
     31 1. Erase /opt/colli-instances/www.engagemedia.org files 
     32 1. Install new Plumi 3 site under /opt/colli-instances/www.engagemedia.org 
     33 1. Migrate data from Plumi 0.2.x installation to www.engagemedia.org '''(complete by 2010-04-15 12:00 GMT)''' 
     34 1. Apply new engagemedia.org theme from testing.engagemedia.org into www.engagemedia.org 
     35 1. Test to verify new www.engagemedia.org is operational '''(complete by 2010-04-15 14:00 GMT)''' 
     36 1. Open engagemedia.org to the public '''(complete by 2010-04-15 16:00 GMT)'''